Echo Summit Bridge
Together with Q&D we came up with a cut plan, pick plan and hazard analysis to complete this total bridge demo and build back with only a 7 day complete closure for Hwy 50. The job was completed safely and Penhall’s scope was completed a full day earlier than allotted in the schedule. To complete this job we core drilled pick holes for the bridge deck to be removed in sections and crews flat sawed bridge deck into panels for removal. We wall sawed to separate bridge abutments and rock retaining walls