Colorado River Aqueduct Project
- One of the main challenges was the jobs’ location, in the middle of the desert in Southern CA. All personnel, equipment, generators, supplies, fuel and sources had to be strategically brought in and stored in the desert.
- Work was done around the clock. Crews switch off between 12-hour day and night shifts.
- The project required precision of both vertical and horizontal cuts using wall and hand sawing.
- Cutting was immediately followed by Penhall’s demolition crew who used excavators to remove the damaged concrete sections.
- Eight wall saws ran day and night to perform the cutting and complete the project on time In all, 20,000 cubic feet of concrete was removed from the CRA.